Progress report on E. O. Ry. For June 8th.



					Eastern Oklahoma Ry.
					Office of Resident Engineer
					June 8, 1900
					Guthrie, Oklahoma


Mr. James Dun,
Chief Engineer,
Topeka, Kans.

Dear Sir:--

TRACK laid into Pawnee. Passing, House and industrial tracks in Pawnee, completed. Wye will be completed to-morrow. Track between Glencoe and Pawnee is practically all unsurfaced. Will have surfacing gang at work Monday.

WATER SERVICE Water stations at Iowa City and Ripley completed. Small water tank one mile East of Stillwater completed. Pump erected one half mile West of Pawnee, pumping direct into Engine tank. Temporary tank will be erected at once.

BRIDGES Two Home Truss spans on East end of Cimarron river bridge completed-working on third span. Piers and abutments all completed. Piles all driven on Upper Stillwater bridge and driver working on Lower Stillwater. Will commence unloading iron girders, and I beam to-morrow.

FENCING On the E. O. Ry. Will be completed next week.

BUILDINGS and STOCK YARDS at Stillwater completed. Depot at Glencoe three-fourths completed. Depot at Pawnee will be started Monday.

Yours truly,

H. C. Phillips
W.H.

Resident Engineer.

D-WH

Page 87 Volume 23 Splinters transcribed in altered form for the web by Russell Crump

Back, Forward


The Splinters - Volume 7 | The Splinters - Volume 12 | The Splinters - Volume 14 | The Splinters - Volume 19 | The Splinters - Volume 23


ATSFRY.com
Home Page

Junction Records

Plans & Plats

Oral history

Train Orders

Photo
Archive

Clicbooks

Available
E. Archive

The
Splinters

Meades
Manual


Site maintained by Russell Crump all rights reserved© 913-962-4556 73077.2356@compuserve.com
Added to the WWW 09-26-97
Updated 05-26-2003