
Page 7 (continued)
The following is the estimated cost of completing the Outer Belt from Turner (Orient and Santa Fe Connection) to Second Street, (Missouri Pacific Connection) and to Eighteenth Street (Kansas City Belt Railway connection).
The estimates are based on a double track line.
Right of Way..............................$24,000.00 Grading.................................. 67,000.00 Kaw River Bridge..........................560,000.00 Other Bridging............................ 60,000.00 Main Line Track - 80 #....................136,000.00 Sidings - 60#............................. 46,000.00 Ballast................................. 52,000.00 Buildings................................. 51,000.00 ................. Total....................................$996,000.00Page 8
KCOB&E report transcribed in altered form for the web by Russell Crump
INDEX
Introduction..................................................1 Kansas City, Outer Belt & Electric R.R........................3 Estimate of Cost.........2 maps.......................7 Map......................1 map........................8 Newspaper clippings.....1 map....................9 &10Kansas City, Mexico & Orient Ry. (to be transcribed some future date).....................11-127