TABLE OF ESTIMATES

Cubic Yds. Earth Excavation
1,936,740
at 17¢
$ 329,245.80
Cubic Yds. Solid Rock
16,280
at $1.25
20,350.00
Cubic Yds. Loose
8,140
at 75¢
6,105.00
Cubic Yds. Earth in Foundations
2,000
" 25¢
500.00
Cubic Yds. Earth in Sidings
40,000
" 17¢
6,800.00
No. of Acres Clearing & Grubbing
860
" 20.00
17,200.00
No. of Miles Iron of 56lbs & trimmings
142.50
"(4000.00
570,000. )
No. of Miles of Tracklaying
142.5
"$ 450.00
64,125.00
No. of Cross Ties
376,200
" 48¢
180,576.00
No. of Sets of Switch Connections with frogs
22
"$ 60.00
1,320.00
No. of Sets switch ties
22
40.00
880.00
No. of Crossings
3
500.00
1,500.00
No. of Cattle Guards
232
30.00
6,960.00
No. of Road Crossings
300
5.00
1,500.00
       
       
       
       
       
       
       
       
       
       
       

            	                			               
          			
                                 		
 					                           
   			                       		 
  		   
 
 		 
  
 "  "  Feet Truss Bridging				                 450         "   40.00		18,000.00
 "  "  Bridge Seats					                       6         "  400.00		 2,400.00
 "  "  Feet Trestle Bridging			            	24,932       "    5.00     124,660.00
 "  "  Section Houses				                      14         "  500.00		 7,000.00
 "  "  Depot Buildings 					                  11         " 1000.00		11,000.00
 "  "  Water Stations				                       7         " 1000.00       7,000.00
 "  "  Locomotives 30 Tons				                   5         "(8500.00		42,500.00)
 "  "  Flat Cars					                      60         " (400.00		24,000.00)
 "  "  Hand Cars					                      14         " (125.00		 1,750.00)
       Location Engineering									 						 5,000.00
       Construction   "     &
               Superintendence									                    12,000.00
       Engineering instruments &
               Stationery									                         1,200.00
											                                      ____________
											                                 *( $1,463,571.80)

* Reported to Mr. Rosenberg July 9, 1877

(Note: Amounts shown in parentheses were not shown on Impression Copy of B.M. Temple's estimate. However, J.P. Fresenius' Report to Henry Rosenberg of July 9th, 1877 he gives "Cost from B.M. Temple's starting point to Belton as $1,463,571.80 and in B.M. Temple's Report of July 21st, 1877 to J. P. Fresenius he says the prices allowed in the second estimate are the same as on the first line. Using these amounts for the quantities shown, the total checks the amount reported to Mr. Rosenberg.)

								     J. N. O.

Volume 7 Splinters page 145 transcribed in altered form for the web by Johnnie Welborn, Jr.

 

Go back to previous section,Go to next section

The Splinters - Volume 7 | The Splinters - Volume 12 | The Splinters - Volume 14 | The Splinters - Volume 23


Added to the WWW 02-17-2003
Updated