: From : To : Date : In relation to:
E W Grant J Dun 7--17-99 Jones will take locating
party in Okla.
H E Asp E D Kenna 7--18-99 Asking you to name personnel
for new company.
E D Kenna James Dun 7--20-99 There is nothing to interfere
surveying east of Guthrie
Charter 7--24-99 Directors and corporators
F M Asp James Dun 7--26-99 I have been on lookout for men
H E Asp James Dun 7--26-99 On reading again The Act
of March 2, 1899, etc.
H L Marvin James Dun 7--28-99 Have arrangements made to
start parties
James Dun E. Wilder 7--28-99 Introducing Mr. H T Richards
James Dun H L Marvin 7--28-99 The following arrangements have
been made for parties
James Dun H L Marvin 7--28-99 (Continued) The following
arrangements have been made for parties
H E Asp James Dun 7--30-99 Sent to Kenna papers for
execution by Ripley
H E Asp James Dun 7--31-99 Ought we start this survey
before we get permission from the
Secretary of the Interior?
James Dun H L Marvin 7--31-99 Locate the road with Maximum
grade 0.6% Maximum curve 2 degree
Contract 8-01--99 For right of way with Guss & Coyle
A C Touner Britton & Gray 8-02--99 The Acting Secretary has given
permission to survey
Britton & Gray E D Kenna 8-03--99 I enclose letter of 2d from A C Touner
James Dun E D Kenna 8-09--99 Letter from A C Touner gives us
permission to go ahead
James Dun W G Smyser 8--14-99 Write Marvin full instructions
about maps
Supplemental contract 8--31-99 Secretaryâs No 13292-A
James Dun H L Marvin 9--1--99 How railroads secure right of way
under the law
volume 23 page 4
-2-
: From : To : Date : In relation to
H U Midge James Dun 9-9-99 Using B cross as Gen'l Forman
of bridges buildings and water service.
James Dun E P Ripley 9-17-99 Estimates for E. O. And other lines.
H C Phillips James Dun 10-3-99 Am sending you profile for 1st
20 miles.
John A. Phillips James Dun 10-5-99 Sends estimate for Section 3 to 20.
H C Phillips James Dun 10-14-99 General condition of grading work.
E P Ripley James Dun 10-23-99 Citizens of Guthrie protest starting line to Kingfisher from Seward.
H C Phillips C D Purdon 11-18-99 Excursion train to Campbell
H E Asp James Dun 11-21-99 Contract says line must be complete by Jan. 1.
James Dun E P Ripley 12-12-99 Spent last week on Eastern Oklahoma to get at the status of the work
F C Maegley James Dun 12-13-99 Please give dates when E. O. Will be completed
James Dun E P Ripley 12-29-99 Am sending maps from River to Pawnee H C Phillips James Dun
H C Phillips James Dun 1-3-00 On 1st a passenger coach was carried from Guthrie to Perkins and return
Time table No. 1 1-4-00 Limits: Guthrie to Perkins
H C Phillips James Dun 1-5-00 Hold up estimates untill contractors sign
H C Phillips James Dun 1-08-00 Submits estimates for sundry contractors
H C Phillips James Dun 1-19-00 Progress report
H C Phillips James Dun 2-07-00 Daily track laying reports
Time Table No. 2 2-19-00 Limits: Guthrie to Ripley
H C Phillips James Dun 2-23-00 Progress report
H C Phillips James Dun 3-08-00 Track is now surfaced Guthrie to Ripley
H C Phillips James Dun 3-22-00 Progress report
Time Table No. 3 3-25-00 Limits: Guthrie to Stillwater
H C Phillips James Dun 3-30-00 Progress report
Time Table No. 4 4-01-00 Limits: Guthrie to Stillwater
H C Phillips James Dun 4-26-00 Progress Report
H C Phillips James Dun 5-4-00 Progress Report
H C Phillips James Dun 5-18-00 Progress Report
James Dun E P Ripley 5-20-00 Estimates to complete E.O.
H C Phillips All concerned 5-31-00 On June 1st Operating Dept takes over
volume 23 page 5
-3-
: From : To : Date : In relation to
H U Mudge Heads Depts 5-31-00 At midnight tonight
H C Phillips James Dun 6-1-00 Have been to busy to make reports
H C Phillips James Dun 6-1-00 Bailey has accepted track to Stillwater
H C Phillips James Dun 6-8-00 Progress Report
H C Phillips James Dun 6-15-00 Progress Report
James Dun H U Mudge 6-18-00 Dates when track reached various stations
James Dun Certificate 6-20-00 Certifies that track was completed to Pawnee
H C Phillips James Dun 6-22-00 Progress Report
H C Phillips James Dun 6-29-00 Progress Report
H C Phillips James Dun 7-13-00 Progress Report
H C Phillips James Dun 7-20-00 Progress Report
James Dun H C Phillips 8-9-00 Rip rap at Cimarron Bridge thoroughly (First letter from Dun in Chgo)
James Dun A F Robinson 8-16-00 Strength of Howe Truss
James Dun H C Phillips 8-17-00 Relative to turning track over as far as Pawnee
James Dun H C Phillips 8-30-00 Let Howe go
James Dun E P Ripley 9-7-00 Progress report
James Dun W B Storey 9-12-00 To relieve Phillips please instruct W H Earl to take charge after Sept 15th.
James Dun E P Ripley 9-15-00 Progress Report
James Dun E P Ripley 9-25-00 Progress Report
H C Phillips All Concerned 9-25-00 Turning over all parts of the work.
James Dun H C Phillips 9-26-00 Your work is highly appreciated
H C Phillips W B Storey 10-8-00 Dates when operating dept took charge
H C Phillips W B Storey 03-09-01 Connection of fCross Welles and Woodbury Howe with B&B work on E.O.
Anonimous Distance between E.O. stations.
volume 23 page 6
The Splinters - Volume 7 | The Splinters - Volume 12 | The Splinters - Volume 14 | The Splinters - Volume 19 | The Splinters - Volume 23
ATSFRY.com |
Junction Records |
Plans & Plats |
Oral history |
Train Orders |
Photo |
Clicbooks |
Available |
The |
Meades |
Added to the WWW 12-04-96
Updated 10-23-2000
Site maintained by Russell Crump all rights reserved© 913-962-4556 73077.2356@compuserve.com